Skip to content
LGCMI H-Project Battery Manufacturing Facility

Client

LG Chem Michigan, Inc.

Location

Holland, Mich.

Market

Size

615,000 SF

Delivery Methods

Design-Build

The LG Chem Michigan (LGCMI) H-Project consists of 615,000 square feet of manufacturing, assembly and storage space for lithium-ion battery production targeted for use in electric and hybrid electric vehicles (EV/HEV). Plant construction includes corporate offices, production and assembly areas and 120,000 square feet of special clean and dry rooms.

Roncelli, Inc. was selected as the project’s design-builder primarily because of it’s aligned culture, shared values, understanding of critical manufacturing process and its commitment to deliver exceptional results consistant with LGCMI’s business objectives.

The entire design-build process, including the installation of manufacturing equipment, was completed within fifteen months. The project schedule included five key milestones to turnover critically sequenced areas for LGCMI’s testing and validation of the manufacturing processes. Roncelli also assisted in the equipment startup and led the commissioning process for all systems.

The H-Project is a critical component to LGCMI’s natural progression to establish cell and pack assembly capability within the U.S. The completion of this facility will demonstrate their commitment to meet automotive customer product demand and requirements.

“…construction was ahead of schedule…(and) the planned start of production has been moved up three months.”  Kee Eun, Business Planning Director, LG Chem Michigan, Inc. – at Holland Area Chamber of Commerce’s Early Bird Breakfast presentation, September 12, 2011.

 

The LGCMI H-Project, located in Holland, Michigan is the first of three phases of proposed plant construction and consists of 615,000 square feet of manufacturing, assembly and storage space for lithium-ion battery production targeted for use in electric and hybrid electric vehicles (EV/HEV). Plant construction includes corporate offices, production and assembly areas and 120,000 square feet of special clean and dry rooms.

The start of construction will coincide with the completion of the project’s building design, which seamlessly integrates the owner’s process and manufacturing equipment. The entire design-build process, including the installation of manufacturing equipment, will be completed within fifteen months. The project schedule includes five key milestones for turnover of critically sequenced areas for LGCMI’s testing and validation of the manufacturing processes.  Roncelli will also assist in the equipment start up and lead the commissioning process for all systems.

Related Projects

Western Michigan University Davis Dining Hall Food Service Renovations

Project name
Western Michigan University Davis Dining Hall Food Service Renovations
Location
Kalamazoo, Mich.
Size
6,000 SF

Skywalk Security Upgrades

Project name
Skywalk Security Upgrades
Location
Detroit, MI
Size
1,500 SF

Regal Cinemas 12 Theatre – Westfield Plaza Camino Real

Project name
Regal Cinemas 12 Theatre - Westfield Plaza Camino Real
Location
Carlsbad, CA
Size
58,615 SF

Get to know us better

Want to learn more or get started building with us? Fill out the form below and a Roncelli team member will reach out to you shortly!